Whether your generator is a 20kw or a 2 megawatt utilizing a load bank to test the generator s functionality will help detect.
Generator load bank testing cost.
Each step to last fifteen 15 minutes record engine and generator data as detailed later in this section.
It is important to test your generator on a regular basis.
For example if a generator is used as a backup for services associated with loss of life or serious injury such as in a hospital setting the testing requirements are much more frequent.
During load bank testing data can be recorded that offers a more thorough look into the health of the gen set on the whole.
6 4 4 1 1 2 specifies that the 10 second criterion does not apply during the monthly testing of the generator.
It verifies that all primary components of the generator set are in proper working condition under loaded conditions.
A load bank checks the engines ability to perform and provide the required horsepower when called upon in an emergency.
The equipment used to conduct a load bank test produces artificial loads on the generator by bringing the engine to an appropriate operating.
Generator load bank testing.
Reactive inductive load bank to test generators turbines backups or air conditioning systems at 0 8 power factor test loads of your power sources up to 3 000 kvar ideal for commercial or industrial duty.
O engine exhaust temperature during test if applicable p kw load under test q identification of unsatisfactory conditions and corrective action taken including parts replaced note.
A generator load bank test involves an examination and assessment of a genset.
The frequency schedule for load bank testing on a generator often depends on how the generator is classified and what it is a standby for.
Power electrics use a load bank testing service to test your generator to its full capacity without disrupting the power supply to the building.
Power system specialists recommend testing the generator systems once a year at full load with a load bank.
Hard wiring the load bank for each test adds significant cost to an annual service agreement.
Load bank testing is the process of using a mobile load bank to accurately mimic the operational load that a generator can achieve.
Saving time is especially important during urgent needs including medical testing screening centers and temporary hospitals.
2 in lieu of nfpa 110 5 13 2 3 h i hook up the dry type load bank to generator and perform a stepped load test on the generator at 25 50 80 and 100 of the nameplate kw rating of the generator.